Unitel Engineering has completed the reconstruction of the 500 kV Novo-Anzherskaya substation in Siberia
«Unitel Engineering», a member of the «NEC» industrial group, has successfully and rapidly completed a complex of works on the reconstruction of the 500 kV Novo-Anzherka substation in Siberia. The project, completed within two months, involved the creation of an independent emergency protection system that enhances the reliability of the power grid and the stability of electricity supply to consumers.
The project included the following works:
- Development of working documentation;
- Selection and coordination of working frequencies of high-frequency channels with the regional frequency holder for the 110 kV high-voltage transmission lines (Novo-Anzherka–Yayskaya and 110 kV Novo-Anzherka-Iverka);
- Supply, installation, and commissioning of equipment (emergency protection automation, high-frequency processing, fiber optic communication lines);
- Author supervision.
«Completing projects for the reconstruction of significant substations in the Siberian region improves the stability of electricity supply to consumers and the overall reliability of the power grid – thanks to the reservation of the emergency protection system of the branch of PJSC Rosseti – MES Siberia», emphasized Mikhail Yurievich Maksyuk, the project's chief engineer.